Wednesday, 26 October 2011

Will St Forest Hill

Weeks Two and Three – 29th October – 13th October

Week Two got off to a great start with the completion of the internal demolition and the commencement of the levelling and excavation in the back yard.

Unfortunately, rain slowed progress on the excavation of the footings during the second half of week two, in early week three, the excavator had made good progress, finishing off all remaining levelling in the backyard and trenches for strip footings.  Stump holes were also dug and in week three, the brickies were on site laying the base brickwork on the strip footings. 

The completion of the footings meant that an inspection from the building surveyor was made and the builders were given the all clear to proceed with the sub-floor framing.  Pretty mucky stuff ….




Stay tuned for next week's instalment .... Sub Floor Framing ...

No comments:

Post a Comment